CAPITAL PROJECTS FUNDED BY THE VOTER-APPROVED HALF-CENT SALES TAX INCREASE

In November 2018, Martin County voters generously approved a half-cent sales tax increase to provide funding for a variety of critical capital projects in the Martin County School District.


Please bookmark this page to review current and ongoing maintenance, repair, construction and facility enhancement projects throughout the District.

***Full Capital Project List (2018-2026)*** 

Project Status Update - November 2021

Bessey Creek Elementary School - Chiller Plant Pump Replacement, Security Camera Installation.

Chiller project is in process, camera installation is complete. 

Citrus Grove Elementary School - Security Camera Installation, Front Lobby Hardening

Camera installation is complete. Lobby hardening project is underway.

Crystal Lake Elementary School - Gutter Replacement, Security Camera Installation

Both projects have been completed.

Dr. David L. Anderson Middle School - Outside Air Damper and Chiller Rebuild, Camera Installation 

Projects complete.

Dr. David L. Anderson Middle School - Roof Repair Building 4

Project has been completed.

Felix A. Williams Elementary School - Gutter Replacement, Security Camera Installation

Both projects have been completed.

Hobe Sound Elementary School - Security Camera Installation

Project has been completed.

Head Start Programs - Point of Entry Control

Project Underway

Hidden Oaks Middle School - Covered Walkway Extension, Security Camera Update, Perimeter Fencing

Covered walkway project has been completed. Camera updates and fencing are in progress.

Indiantown Middle School - Front Lobby Hardening Project

Construction underway.

J.D. Parker Elementary School - Chiller Refurbishment, Gutter Replacement, Security Camera Installation, Front Lobby Hardening

Chiller Refurb - Complete

Gutter Replacement - Complete

Camera Installation - Complete

Lobby Hardening - Under Construction

Jensen Beach Elementary School - Complete School Replacement

June 16, 2020 - The Martin County School Board approved staff's recommendation to award the Construction Management at Risk Services (CMR) Pre-construction Services contract for the replacement of Jensen Beach Elementary School to Proctor Construction Company, LLC.  The negotiated CMR Pre-construction Services Contract includes the cost and scope for services on the project. 

 July 21, 2020 - Chief Operations Officer Garret Grabowski presented architectural renderings to the School Board. 

 August 18, 2020 - Chief Operations Officer Garret Grabowski presented a project update to the School Board.  

September 24, 2020 - District staff will join representatives of Harvard Jolly Architecture in presenting a virtual update to the community.  

July 20, 2021 - The School Board approved the Guaranteed Maximum Price (GMP) which will allow construction to begin. Groundbreaking took place on July 27, 2021.

Jensen Beach High School - Flooring Replacement

Project complete

Jensen Beach High School - Building 6 Roof Replacement

Project complete.  The auditorium roof is underway. 

Jensen Beach High School - Enhanced Security: Fencing, Tennis Court Replacement, Flooring Replacement, Roof Replacement - Building 6, Water Intrusion Remediation

Perimeter security updates are underway. The tennis court and flooring have been replaced. The roof has been replaced. Water intrusion repairs are underway.

Martin County High School - Safety Improvements, Cafeteria & Music Building Repairs

The enhanced security projects have been completed.

Palm City Elementary School - Complete School Replacement

June 16, 2020 - The Martin County School Board approved staff's recommendation to award the Construction Management at Risk Services (CMR) Pre-construction Services Contract for the replacement of Palm City Elementary School to Paul Jacquin & Sons, Inc. The negotiated CMR Pre-construction Services contract includes the cost and scope of services on the project. 

July 21, 2020 - Chief Operations Officer Garret Grabowski presented architectural renderings to the School Board.  

August 18, 2020 - Chief Operations Officer Garret Grabowski presented a project update to the School Board.  

September 24, 2020 - District staff will join representatives of Harvard Jolly Architecture in presenting a virtual update to the community.  

July 20, 2021 - The School Board approved the Guaranteed Maximum Price (GMP) which will allow construction to begin. Groundbreaking took place July 27, 2021.

 Pinewood Elementary School - Water Intrusion Repairs, School Intercom Replacement, Security Camera Installation

Projects have been completed.

Port Salerno Elementary School - Security Camera Installation

Project has been completed.

Seawind Elementary School - School Intercom Replacement, Camera Installation

Both projects have been completed.

Stuart Middle School - New Admin & Media Center buildings, New Cafeteria and multipurpose buildings, new power plant building

Projects are currently under review and being negotiated with vendors.

South Fork High School - Sports Complex & Fields, Site Drainage System and Chiller Plant/HVAC System Replacement

The projects are currently in the GMP process - subcontractors are bidding at this time.

South Fork High School - Golf Course Revitalization

Project Underway

Warfield Elementary School - Security Camera Installation, Front Lobby Hardening

Camera installation is complete. Lobby hardening is underway.

Willoughby Learning Center - Air Handler Unit Replacement, Camera Installation

Both projects have been completed.